With the nearby Binhai North District H2 # sea wind power project part of the fan grid power generation, our province's sea wind power and net loaded machine has exceeded 2 million kilowatts, accounting for nearly 70% of the national scale, continue to lead the country.
Modified planning compression
Based on the high-affected development conditions that have a high impact of the typhoon and other disasters such as rich beach resources and sea wind energy, our province is the only thousands of kilowatt sea wind power bases determined by the country. In recent years, the province has focused on renewable energy represented by maritime wind power, and proposed to the development goals of "accumulating 3.5 million kilowatts, accumulated 4.5 million kilowatts, accumulated 3 million kilowatts" in 2020.
"Jiangsu Province Haimen Wind Farm Engineering Plan" is a blueprint for the development of sea wind power industry in our province. Since the implementation of the state in 2012, it has played a very important role in norms, leading and promoting the construction of sea wind power in our province. "Due to the continuous adjustment of marine ecology and sea management in the second half of 2016, it will further implement national development strategies, adapt to policy adjustments, and make planning more feasible, operability, and better serve our province. The wind power industry has developed, last year, our province took the lead in planning and repairing in the country. Currently, the revolutionary work has been completed and will be reported to the country. "Provincial Development and Reform Commission said.
According to unified planning, installment implementation, efficient use, saving sea, environmental protection concept, the revolutionary planning further compresses the sea area, coordinating resource allocation, initial planning site, the total installed capacity is 14.75 million kilowatts, total area 2614 square kilometers, more than 2.2 million kilowatts of total planned head-loaded machines, reduce 1067 square kilowats with sea area. Scientific Repair of "Jiangsu Province Haimen Wind Farming Project Plan", in order to achieve the goal of "Jiangsu Province" 13th "Renewable Energy Development Special Planning" goal lays a solid foundation.
Explore innovative development management mode
The new old kinetic energy conversion is directed around energy change, and our province adheres to the unified planning of "Jiangsu Province Haimen Wind Farm Engineering Plan", in order to develop offshore wind power resources, and actively explore the development model and management model innovation. Focus development model begins innovation. In our province's insistence on the principles of overall development, in response to the different characteristics of the sea wind farm, promote different forms of advanced development programs, and coordinate the development of various preliminary work. Vigorously promote the development model of sea wind power, by packaging project design, construction, material equipment procurement to a professional unit, "let professional people, doing professional things", minimizing offshore wind power construction investment costs and Quality maximizes.
Promoting the "Quad - 1" Construction Mode of Maritime Wind Power. The National Electric Power Binhai North H1 Area 100 MW sea wind power project is the first sea wind power project in my country's sea wind power to be built in the "four-in-one" manner. "Siyi 1", the fan, tower tube, piling, and installation fans are undertaken by a company. This mode is started to show market competitiveness. October 2015 project started, until June 2016, the construction speed of the project is unique in the history of domestic sea wind power development. "This project has a number of scientific and technological achievements to fill in domestic sea wind power construction technology. For example, it can generate 100 million degrees per hour. It can save approximately 81,300 tons per year, reduce sulfur dioxide from 1977.95 tons, nitrogen oxides 1700 tons, CD of 194,000 tons of carbon dioxide. "Chen Lizhi, deputy general manager of Jiangsu Maritime Wind Power Co., Ltd., said that the second phase of 400 MW project is accelerating, the third phase of 300 MW project plans started next year, after the project was completed, the national electric investment Binhai Haimen Wind Farm will become a single largest sea wind farm in the country.
Innovation around the management model. In order to establish a new sea wind power safety management system, our province has proposed corresponding construction safety measures and emergency plans for different working faces, and puts new heights in offshore wind power safety production. "Smart" sea management, develop the "Internet +" new form of sea wind power, building an efficient sea operation and maintenance system, using large data processing management control fan status, so that the unit availability and power generation are guaranteed, realize smart operation and maintenance, remote monitoring ,Troubleshooting.
Bringing equipment technology development with project construction
In response to the start of the sea, the development level, the technology creation, equipment manufacturing, etc., the province has a certain gap in developed countries, and our province passed strengthening international cooperation, especially the company and the United Kingdom, the Netherlands, Germany, Denmark and other sea wind power. Corporate exchange and cooperation, through the establishment of joint ventures, hired international high-end technical talents, introducing foreign advanced equipment technology, combined with foreign agricultural equipment, mastering wind power manufacturing key technology, achieving continuous improvement in the province's sea wind power technology .
Taking the construction of the project as the starting point, carrying the development of equipment technology. Such as the large-diameter unparalleled single pile infrastructure used in the Dongchao-wind farm project, due to reducing the advantages of maritime construction work, improved effectiveness, reduced safety risks, saving filling materials, etc.; Three Gorges The first domestic voltage level used in 200 MW off-sea-style electric field projects, the longest length, the largest cross section, marking the province's sea cable production technology continues to go in the country in the country; Datang Binhai 300 MW sea The 80 kV sea boosting station built by the wind farm project was built, and the 220 kV sea boosting station, which deepened the deepest, representing our province's new technological breakthrough in this field. At present, the construction of wind farm project in our province is still the first in the country and the world, and has accumulated experience in the construction and construction of the wind farm in the chalk, and the development of sea wind power is developed and demonstrated. Read the full article, original text title: sea wind power, please see Jiangsu leader